State Route 67 Bridge Repair
Elizabethton, TN · Bridges · 2025 · Client: Tennessee Department of Transportation (TDOT)
Project details
Following damage from Hurricane Helene in September 2024, the Michels-DBA design-build team repaired and lifted the concrete arch span bridge in Elizabethton, Tennessee. The project involved de-watering, installing micropiles, designing steel shoring frames to support jacks under each column, demolishing undermined footings, jacking the bridge 4.5 inches to restore structural integrity, and constructing a new pile cap.